One of the most common questions from Dubai homeowners planning a renovation is: “How long will it take?” The honest answer is that renovation timelines in Dubai depend on many factors — scope, building management approvals, material procurement, joinery production, site access, and the contractor’s schedule.

This guide by ASM Interiors by Asfar Majeed Technical Services LLC provides realistic renovation timelines for different project types in Dubai and explains the key factors that influence how long a renovation takes.

1. Typical Renovation Timelines in Dubai

Below are realistic timeline ranges for common renovation types in Dubai:

Renovation TypeTypical Timeline
Kitchen renovation (medium size)4–7 weeks
Bathroom renovation (standard)3–5 weeks
Bathroom renovation (full master)4–7 weeks
Full apartment (1-bed)6–10 weeks
Full apartment (2-bed)8–14 weeks
Full apartment (3-bed+)10–18 weeks
Wardrobe installation (supply only)2–4 weeks
TV wall installation1–3 weeks
Full villa renovation12–24+ weeks

Note: These timelines are after building management approval is received and materials are ordered. Approval, procurement, and planning add time on top of these estimates.

2. Pre-Construction Timeline Phases

Before any site work begins, the following phases must be completed:

Phase 1: Site Visit and BOQ Preparation (1–2 weeks)

Site visit, measurement, scope confirmation, and preparation of a detailed BOQ. Depending on project complexity, this may take 3–10 working days from initial site visit to final BOQ delivery.

Phase 2: BOQ Review and Client Approval (1–2 weeks)

Client reviews the BOQ, requests changes, and provides final approval. Multiple review rounds may extend this phase if scope changes are made.

Phase 3: Building Management NOC Application (1–3 weeks)

Building management NOC application is submitted and processed. Simple NOC approvals typically take 3–10 working days if all documents are ready. Buildings with strict approval processes or backlogs can take 2–3 weeks.

Phase 4: Material Selection and Procurement (2–6 weeks)

Material selection (tiles, flooring, sanitaryware, hardware, lighting) must be finalised before or during the approval phase. Most tiles and standard materials are available from local UAE stock within 1–2 weeks. Imported or special order items can take 4–8 weeks. Joinery production typically takes 3–5 weeks after design finalisation.

3. On-Site Renovation Phase Timeline

Once building management approval is received and key materials are ready, the on-site renovation follows this typical sequence:

Demolition

Removal of existing tiles, flooring, ceilings, fixtures, and old joinery. Duration depends on scope. A full apartment demolition typically takes 3–7 working days. Building management noise restrictions may extend demolition time (heavy chipping typically only permitted during specific hours).

Structural and MEP Works

Any wall modifications, electrical DB works, plumbing re-routing, or AC duct adjustments are done after demolition. Duration: 1–3 weeks depending on scope.

Waterproofing

Bathroom waterproofing (two coats + flood test): 5–7 working days per bathroom, including curing time between coats and flood test period.

Screed and Levelling

Floor screed application and curing: typically 5–7 days before tiling can proceed.

False Ceiling Works

Gypsum board false ceiling installation (where specified): 1–3 weeks depending on complexity and area.

Tiling Works

Floor and wall tiling. Duration depends on tiled area size and tile format. A full apartment: 2–4 weeks for tiling including setting time before grouting.

Joinery Installation

Custom joinery (kitchen, wardrobes, TV walls) is typically installed after tiling and ceiling works are complete. Installation duration depends on number and size of items. A full apartment joinery installation: 1–2 weeks.

Painting

Wall and ceiling painting after joinery installation: typically 5–10 working days for a full apartment including primer and final coats.

Fixture and Fitting Installation

Sanitaryware, kitchen appliances, lighting fixtures, switches, mirrors, and accessories: 3–7 working days.

Snagging and Final Handover

Final walkthrough, snagging list completion, cleaning, and handover: 3–7 working days depending on snagging items identified.

4. Common Causes of Renovation Delays in Dubai

5. How to Reduce Your Renovation Timeline

Frequently Asked Questions — Renovation Timeline Dubai

Q1. How long does a kitchen renovation take in Dubai?

A typical kitchen renovation in Dubai takes 4–7 weeks from demolition to handover, depending on scope, tile area, and joinery complexity. Add 2–4 weeks for pre-construction planning, approval, and material procurement.

Q2. How long does a bathroom renovation take in Dubai?

A standard bathroom renovation in Dubai takes 3–5 weeks from demolition to handover, including waterproofing, tiling, and fixture installation. Master bathrooms with more complex scope take 4–7 weeks.

Q3. Why does renovation take longer in Dubai than expected?

The most common reason is delayed material procurement due to late material selections. Building management approval delays and scope changes mid-project are the second most common causes of extended renovation timelines in Dubai.


Get a Realistic Renovation Timeline from ASM Interiors

ASM Interiors provides a detailed project timeline as part of every renovation BOQ. We confirm realistic timelines after the site visit — we do not promise unrealistic delivery dates to win a contract.